Risk Action Report

This report enables the user to filter and generate reports pertaining to Risk Solutions (i.e. mitigation actions). The report can be filtered by DIRECTORATE, Business Unit, Team, Risk Status (Active, Inactive) and Risk Type (Strategic, Operational or Project) if required.

A set of three options Proposed, Complete and Overdue enables further filtering as follows:

 

FILTERS

Filters:

Business Rules

Risk Type

Will allow the user to select the type of risk & filter the report content accordingly. Default to ‘Show All’.

Directorate

Lists the available Directorate s within the Organisation and must filter the risks according to the Directorates selected by the user. Default to ‘Show All’.

Business Unit

Lists the available Business Units within the Organization and must filter the risks according to the Business Unit selected by the user. Default to ‘Show All’.

NOTE: If the ‘Risk Type’ is selected as ‘Strategic Risk’ then selecting a ‘’DIRECTORATE' or ‘Business Unit' will effectively give a blank report since those risks do not have a direct link to these areas.

Risk Report

A set of three options Proposed, Complete and Overdue enables further filtering as follows:

· Proposed: Only lists Risk Actions where % complete <100%

· Completed: Only lists Risk Actions where % complete = 100% (default filter)

· Overdue: Only lists Risk Actions where current date > Due date

Risk Status

Will allow the user to filter the report content by the status of risks. Default to ‘Active’.

 

REPORT DETAILS

Report Element

Description

Cover Page

Displays the report title with what Risk Report (status) you have selected (Proposed/Completed or Overdue). Also displays the client logo.

Details

Grouped by Risk type, it will display all risk actions and their details below

Risk Actions

Risk Code

Risk Code.

Risk

Risk title

Risk Action

Risk Action Title

Status

Risk Action Status

% Completed

Risk Action % Complete (YTD)

Responsible Person

Risk Action responsible person

Due Date

Risk Action End Date (Due Date)

Over Due Days

Number of days (YTD) that the risk action has been overdue for.

Initial likelihood

Initial Assessment Likelihood description

Initial Consequence

Initial Assessment Consequence description

Initial Risk Rating

Initial Assessment Rating description and Icon

Current Likelihood

Current Assessment Likelihood description

Current Consequence

Current Assessment Consequence description

Current Risk Rating

Current Assessment Rating description and Icon

Future likelihood

Future Assessment Likelihood description

Future Consequence

Future Assessment Consequence description

Future Risk Rating

Future Assessment Rating description and Icon

Risk Responsible Person

Risk Responsible Person

Review Frequency

Risk Review Frequency (within the risk review tab).

 