This object lets you create tasks for a given project and displays them in a graphical timescale format in a Gantt chart. The fields configured in the Object Editor area are displayed here as shown in the below screenshot.

A text box with auto fill facility will appear for the custom list as shown above and when you type a few numbers or letters, all the matching items for the project will appear.

Hover over any of the coloured bars to see a quick summary.

Any changes done to the Project Table will be automatically updated in the Gantt chart in real-time and vice versa and once a Summary Task is completed, all its Child Tasks are auto updated and vice versa as well.

You can assign multiple resources to a task by clicking on the icon given on 'Responsible Person' column. You need to tick the staff which you need to allocate as resources and click 'OK'. You have to decide the primary resource by ticking the 'Primary' box and it is compulsory that you choose one. You can also see the percentage of involvement through the 'hours per day' which will be decided by the user (double click the 'Hours per day' box in order to edit the value'). See the example given below.

The icons above the Gantt chart can be used to add and delete tasks as necessary, along with many other functions.

Icon

Description

Saves Gantt chart.

Prints Gantt chart information. This provides different options to print.

Refreshes Gantt chart.

Adds a new task to the Gantt chart.

Deletes the selected task from the Gantt chart.

Indents / Outdents the selected task.

Highlights your tasks that you are responsible for (in bold) within the schedule. Clicking the button also clears it.

 

Expands / Collapses the default Gantt chart view to fill the screen.

 

Shows / Hides the critical path within the project schedule

Expands / Collapses the task to show the associated sub tasks.

Create / View Baseline.

Add notes against a Task

Downloads the MS Project Addin - which gives the ability to export the Gantt chart as an XML file which can be then viewed and edited using MS Project. Once edited it can also be imported back into CAMMS Projects (IPM). See 'MS Project Addin' section for more information on this function.

Fits the Gantt chart to show on the page in full.

 

The system uses the following icons to indicate the task progress.

Indicator

Description

'On track'

This is displayed if the activities of a task are going according to the project schedule.

'Monitor'

This is displayed if the task needs to be monitored.

'Off track'

This is displayed if the activities of a task are going behind the project schedule.

N\A

This is displayed when a new task is created. After task details are entered, this is replaced by any of the above indicators.

'No Target Set'

This is displayed if a project does not have a target.

 

 

 

 